10/27 - 10/31 Times:
Monday: 9am - Noon, 1 to 4pm, No work Monday evening (Celebrate Recovery)
Tuesday: 9am - Noon, 1 - 4pm, (Evenings if you call and want to paint)
Wednesday: 9am - Noon, 1 - 4pm, (Evenings if you and and want to paint)
Thursday: 9am - Noon, 1 - 4pm, (Evenings if you call and want to paint)
Friday: NO WORK
Saturday: NO WORK
​
All,
Listed are some things we will be working on this week.
Monday:
Offices: Continue painting.
Hallway: Touch-up painting.
Gym: Remove basketball hoop supports (6 bolts) and fill holes. (North side)
Tuesday:
Offices: Continue / Finish painting.
Gym: Contractors in prepping for painting upper walls.
Wednesday:
Offices: Finish painting.
Install door frames.
Install doors.
Install baseboard trim?
Gym: Contractors in painting.
Thursday:
Offices: Clean-up day.
Contractor hooks up all the electrical outlets and switches.
Gym: Contractors in cleaning up.
Friday:
Contractors come in to clean carpet in all offices and office hallways.​
​